The La Son-Hoa Lien section of the North-South East expressway, 65km long, expanded from 2 to 4 lanes, has total adjusted investment of 3,217.75 billion VND. Package XL1 has reached 94.72% of work volume and basically completed the main lanes, opening 4-lane traffic on **August 31, 2026».

However, after heavy rains at the end of 2025, the entire route saw up to 18 landslide sites on embankment slopes. Contractors are working on 9 sites, while 9 others are stalled due to land clearance issues, concentrated at Km39-Km46 involving Bach Ma forest land.

The investor is working with Da Nang People's Committee to clear additional land, covering 9 landslide sites (9.06ha) and 2 rest stops (6ha). Package XL2 (intelligent transport system, non-stop toll collection, vehicle weight control stations) is expected to complete on **December 31, 2026».

The project targets full completion by December 31, 2026.