Lilama (LLM) has signed an engineering, procurement, and construction (EPC) contract worth over 2.816 trillion VND with Hai Phong Thermal Power JSC (HND) to upgrade the flue gas treatment system at Hai Phong Thermal Power Plants 1 and 2.
The contract is equivalent to over 74.6 million USD and nearly 848.3 billion VND, with an implementation period of 7 months. The contractor selection result was approved under Decision No. 7166/QĐ-NĐHP dated 26/11/2026.
Lilama undertakes all work from design, equipment supply, construction to testing, commissioning and handover for all 4 units. Main items include building a new nitrogen oxide (NOx) removal system using selective catalytic reduction (SCR) technology and an ammonia warehouse; simultaneously upgrading the electrostatic precipitator (ESP), flue gas desulfurization (FGD) system, induced draft fans and auxiliary works.
After completion, NOx concentration at the stack must not exceed 120 mg/Nm³, with NOx removal efficiency of at least 88%, complying with National Technical Regulation on Industrial Emissions QCVN 19:2024/BTNMT. The project is implemented while the plant is still operating, so construction must coordinate with unit outage schedules.
According to EVNGENCO2, the total investment of the flue gas treatment system upgrade project is over 3.607 trillion VND, of which the approved EPC contract value is over 3.124 trillion VND. The plant has total capacity of 1,200 MW, initial investment capital of about 22,000 billion VND. As of 26/11/2026, the plants have supplied about 99.57 billion kWh of electricity, contributed nearly 5.395 trillion VND to the State budget.
Along with signing the EPC contract, Hai Phong Thermal Power also signed a credit provision agreement with BIDV to ensure funding for project implementation.