Deo Ca Group reported progress on Dai Ngai 1 bridge project with total investment of over 3.900 billion VND. The project is over 3km long, with the main bridge section 2.6km long and 21.5m wide.
The bridge is designed as a cable-stayed bridge with two A-shaped towers 110m high from the bridge deck, equivalent to a 35-story building. The main span is 450m, the second largest in Vietnam after Can Tho bridge.
After nearly two years of construction, the bridge has reached 65% of contracted work. Tower P23 has been built to the 25th segment, tower P24 to the 18th segment. Both towers are scheduled for completion in April 2027, followed by cable-stayed cable installation from May 2027.
All 42 piers and approach bridge piers have been completed. Beam formwork volume reached about 97%, Super-T beam erection reached 80%, bridge deck completed 34/42 spans. The contractor consortium mobilized 353 personnel, 85 machines and equipment, and organized 23 construction fronts.
The project is entering the construction phase of items with high technical requirements.
Completion is expected at the end of 2027, with the entire project put into operation from June 2028. When completed, the bridge will replace Dai Ngai ferry, shortening travel time between Vinh Long, Can Tho and neighboring provinces, reducing traffic pressure on National Route 1 and National Route 60.