Phan Dinh Phung indoor arena at 8 Vo Van Tan, Ho Chi Minh City, was built in 1985 and demolished in 2017 after more than 30 years of operation. The replacement project faced many procedural and payment issues, and in April 2024 Ho Chi Minh City switched from the BT (build-transfer) model to public investment capital.
Construction cost is now proposed at 1.850 trillion VND, up from 988 billion VND initially, 1.352.7 billion VND in 2013, and over 1.953 trillion VND in 2016.
The new project is planned with 7 above-ground floors, 3 basement floors, capacity of about 4,000 seats. According to the Ho Chi Minh City Department of Finance (September 2025), the project is scheduled to complete zoning plan adjustment in April 2026, approve investment policy in May 2026, start construction in Q3/2027, and complete in Q1/2029.
While waiting, the site of over 14,000 sqm has been converted into a temporary park from January 2026, serving the community before the new sports project is built.