Deo Ca Group said on 27/11 that advisors Bui Van Ha and Ngo Van Quy inspected the Hoang Lien Pass road tunnel project site. The construction site is mobilizing 176 workers and 68 machines and equipment. On the Lai Chau side, left tunnel excavation reached 180m, right tunnel 45m, main arch reinforcement 90% complete.

The project has capital of VND 3.3 trillion, length of 8.8 km, including main tunnel 2.63km, auxiliary tunnel 2.65km and 11 bridges, started construction on 19/12/2025. The contractor consortium is led by Deo Ca Group.

The tunnel is expected to reduce car travel time from 52 minutes to 11 minutes, trucks and containers from 120 minutes to 11 minutes. The project is considered Vietnam's highest mountain road tunnel, designed to Japanese standards combined with Vietnamese standards.