The Government Office announced the conclusion of Deputy Prime Minister Phạm Gia Túc at the meeting reviewing progress of the investment project for Long Thanh International Airport phase 1.

According to the National Assembly's approved investment plan, phase 1 must be completed and put into operation in 2026. The remaining workload is very large, requiring efforts from all participating entities, especially ACV.

The Deputy Prime Minister required ACV to take full responsibility for progress and quality of project component 3 and packages where ACV is the investor. ACV must also assess the quality of items with errors in sequence and procedures during implementation.

The Ministry of Construction is the focal agency to monitor, inspect, and urge project progress, and report results to the Prime Minister. The Ministry of Construction will coordinate with the Ministry of Public Security to review all necessary conditions for the airport to be put into operation ensuring absolute security and safety.

The Ministry of Public Security was ordered to accelerate investigation and handling of violations and misconduct during project implementation, ensuring clear people, clear actions, clear responsibility. Focus on clarifying the extent of violations at each package and each construction item, including misconduct reported by ACV at the meeting.

The Ministry of Finance will guide ACV to resolve difficulties and bottlenecks related to payment, financial mechanism, appraisal, and exchange rates for imported equipment.

Vietnam Airlines and Vietjet were ordered to accelerate construction of aviation catering services, commercial ground technical works, and Hangars 1, 3, 4.