Minister Tran Hong Minh proposed that from now until December 31, the highway section from Lang Son to Dong Khe commune, Cao Bang province, be opened, putting the Tan Thanh - Dong Khe section (part of Dong Dang-Trà Lĩnh highway) into temporary operation, serving people free of charge during Tet 2027, expected duration 30 days.
The project still faces land clearance issues. According to the project investor, Dong Dang-Trà Lĩnh highway construction project is mobilizing 132 construction fronts, 897 machines and equipment and 2,000 workers. Phase 1 output value reached 9.133/11.663 trillion VND, equivalent to about 78.31%; phase 2 reached 1.425/8.742 trillion VND, equivalent to about 16.3%.
On section Km0 - Km93, road pavement construction and stone spreading have been completed. Asphalt concrete pavement volume reached 78/80km, excluding bridge and tunnel scope. All 64/64 bridges on the 93km section have been completed.
At the new construction section of about 27km, excavation volume reached 0.416/3.906 million m³; embankment volume reached 0.246/3.749 million m³. Contractors have constructed 99/161 bored cast-in-place piles and completed 3/21 bridge piers and abutments. For tunnels, tunnel No. 1 and No. 2 have been completed 1,353/1,353 meters long. Tunnel groups No. 3, No. 3A and No. 4 have excavated 362/1,203 meters long.
GPMB work for phase 1 has been completed. For phase 2, the 93 km expansion section is being implemented; locations with large excavation and embankment volumes are prioritized for handover.
At the 27.7 km renovation section, the locality has handed over 25.5/27.7 km according to 17m roadbed scale. However, land clearance at many locations is still fragmented, not continuous, causing difficulties in organizing synchronized construction.
According to the proposal of the project investor and the operation support unit, Cao Bang Department of Construction has issued a document requesting comments on the plan to organize traffic and the scenario for rehearsing fire fighting, rescue, and salvage on the Tan Thanh - Dong Khe section, from Km0 to Km62.
The project investor requested the People's Committees of Cao Bang and Lang Son provinces to direct relevant functional forces to coordinate with the Vietnam Directorate for Roads to soon agree on the traffic organization plan, rehearsal plan, and coordination mechanism for management and operation to implement in December 2026.
The Ministry of Construction is requested to take the lead, coordinate with the People's Committees of the two provinces to consider and decide on the plan to put the Tan Thanh - Dong Khe section into temporary operation, serving people free of charge during Tet 2027, expected duration 30 days.
The proposal is made under the condition that the phase 2 expansion part has not yet been completed with synchronized acceptance, requiring traffic safety assurance and close coordination among agencies and units throughout the temporary operation period.
Directly inspecting at the project site, Minister Tran Hong Minh requested Cao Bang Provincial People's Committee to soon complete GPMB work, accelerate construction progress. The construction of feeder roads needs attention to build pedestrian underpasses, creating conditions for people to travel.
Minister Tran Hong Minh also proposed that from now until December 31, the highway section from Lang Son to Dong Khe commune, Cao Bang province, be opened. The locality needs to soon have a document requesting the Vietnam Directorate for Roads to guide increasing vehicle speed from 80km/h to 90km/h to suit current standards.
To ensure connectivity, traffic flow; contribute to promoting goods transportation, logistics development and border gate economy, Minister Tran Hong Minh requested Cao Bang Provincial People's Committee to soon complete investment of two connecting roads from the highway to Ta Lung border gate and to the central wards of Cao Bang province. If new construction cannot be implemented immediately, prioritize capital to upgrade old roads, ensuring all routes have 4 lanes to be synchronous with Dong Dang - Trà Lĩnh highway.
The Minister noted that Cao Bang needs to arrange locations, ensure completion of relevant procedures for investors to build 2 rest stops on Dong Dang - Trà Lĩnh highway, ensuring traffic flow and effective operation of the route.
Dong Dang (Lang Son) - Trà Lĩnh (Cao Bang) highway has a total length of 121.06km, design speed 80km/h. Total investment capital is 26.184 trillion VND, including 8.197 trillion VND of investor mobilized capital and 17.987 trillion VND of State budget capital. The project is invested under PPP method, divided into two phases.
Phase 1 is implemented from Km0+000 to Km93+350, length 93.35 km, of which the section through Lang Son province is 52km; the section through Cao Bang province is 41.35km. The scale of this phase is 4-lane limited expressway, roadbed width 17m. The project started construction phase 1 on January 1, 2024, expected to be completed and put into operation in 2027.
Phase 2 expands the section Km0+000 - Km93+350 and builds new section Km93+350 - Km121+060 according to 4-lane full scale, roadbed width 22m. This phase started construction on August 19, 2025, expected to be completed in 2028.