Sóc Sơn waste-to-energy plant, invested by CTCP Năng lượng Môi trường Thiên Ý Hà Nội, was inaugurated in October 2025, becoming the largest waste-to-energy plant in Southeast Asia and the second largest in the world. On average, the plant receives and processes 5,000 tons of waste per day, accounting for nearly 70% of Hanoi's daily household waste.
However, the plant faces a fly ash accumulation problem. Since May 2022, all fly ash has been stored within the plant, reaching over 90,000 tons on more than 1.2 hectares. The plant generates 60 to 75 tons of fly ash per day.
Hanoi has allocated land and approved the landfill procedure, but has not yet identified the implementing unit and the unit to manage the fly ash landfill afterwards. Mr. Đỗ Tiến Dũng, Deputy General Director of CTCP Năng lượng Môi trường Thiên Ý Hà Nội, hopes Hanoi will designate a receiving unit in December this year.
If not removed, the plant faces pressure on space, costs for ground reinforcement, rainwater drainage design, and affects the construction site of phase 2 expansion, potentially delaying the project.
The phase 2 expansion focuses on processing 1,600 tons of buried waste per day, raising the plant's total power generation capacity to 135MW. Total project investment is 12,999 billion VND (over 539 million USD), of which the expansion part is about 5,830 billion VND. The entire plant is expected to operate in Q4 2027.
"In February 2026, we received the city's approval in principle to continue investing in phase 2 of the plant. The fly ash occupying a large area also affects the construction site of phase 2. Therefore, there is a possibility of delaying the project progress." — Mr. Đỗ Tiến Dũng