The Vành đai 3,5 - Đại lộ Thăng Long interchange project in Hanoi has total investment of about 2.384 trillion VND, implemented by the Hanoi Investment Construction Project Management Board for Civil Works. The project started in April 2025 and is expected to be completed in 2027.

After more than one year of construction, progress reached about 38%. Land clearance reached 99.8%, but 3 households in Tây Mỗ ward have not handed over a total area of 342.9 m2, directly affecting construction of pillars belonging to branch 4 and the expanded road connection from Vành đai 3,5 to Đại lộ Thăng Long.

The reason the 3 households have not agreed is failure to agree on compensation levels, saying the offered price is lower than the previous land purchase price from Geleximco urban area developer. 2 of the 3 households have remaining land area after recovery exceeding the minimum allowed for plot separation, so they are not eligible for resettlement policy. Tây Mỗ ward People's Committee has reported to Hanoi People's Committee requesting a decision to resolve the issue.

In addition, underground 110kV and 220kV power cable systems cross directly with bored pile and 4P5 pier locations, causing difficulties in organizing construction.

The project includes 4 flyover branches in trumpet type, total length more than 2.3 km, each bridge width 8.8 m, arranged with 2 lanes, together with an underpass system about 150 m long running underground beneath Đại lộ Thăng Long. When completed, the interchange is expected to improve traffic capacity and increase connectivity in the western area of the Capital.