Minister of Construction Trần Hồng Minh directly inspected and directed at the construction site of the Hữu Nghị-Chi Lăng expressway on the afternoon of 26/11. The project has a total investment of 11.808 trillion VND, about 60km long, passing through 7 communes and wards in Lạng Sơn Province.
Construction progress has reached 82% of the adjusted contract value, equivalent to 7,020.45 billion VND out of a total of 8,544.04 billion VND. Subgrade excavation reached 97.63%, embankment filling 98.52%; asphalt pavement 81.5%, crushed stone base 84.5%.
The investor proposed that Lạng Sơn Province allow temporary free operation of the 36.5km section from Chi Lăng (Km45+130) via Interchange IC03 to the transfer interchange at Km5+325, to serve traffic during the Tet 2027 holiday. The target is to complete the project and finalize acceptance before December 31, 2026.
However, land at 41 locations, Interchange IC04, and rest stops has not yet been fully resolved. The investor requested Lạng Sơn Province to hand over the land before December 15 to construct rest stops and relocate technical infrastructure.
The Minister also asked the Vietnam Directorate for Roads to study increasing the design speed from 80km/h to 90km/h when the route is completed, and encouraged building frontage roads on both sides to serve local economic development.