Deo Ca Group is mobilizing over 400 workers and 117 machines and equipment to work simultaneously on 15 fronts at package XL01 of the Vinh - Thanh Thuy expressway project. The key item is Dai Hue tunnel, where the left bore western portal was opened on September 24, 2026.

According to the plan, Dai Hue tunnel is expected to breakthrough in April 2027 and complete the item in March 2028. The tunnel consists of two bores measuring 495m and 499m, located at the start of the route through Hung Nguyen, Kim Lien and Dai Hue.

The project started on May 18, 2026, with a total length of over 60 km and total investment of 23.940 trillion VND, targeting operation in 2029. Package XL01 is 6.3 km long, including Dai Hue tunnel, 11 bridges and 6 pedestrian underpasses.

Local material supply has not fully met the demand of nearly 9.9 million m3 of fill earth and 995,000 m3 of construction stone, so Nghe An province is increasing quarry output and completing procedures to support contractors.