The Pháp Vân - Tứ Hiệp student dormitory project in Hanoi, with initial investment of 1.900 billion VND, is being renovated and converted in function. Started in 2009 on a land area of over 40,000m², the project includes 6 buildings of 19 floors but many components had been left vacant for a long time.
Hanoi decided to renovate buildings A2 and A3, and build new building A4. Upon completion, these three buildings will provide a total of 1.176 apartments, of which A2 and A3 have 768 units, and A4 adds 408 units. Total investment for this plan is about 1.396 billion VND.
As recorded in late November 2026, overall project progress reached nearly 90%. The apartments are targeted at workers, laborers and groups with rental housing demand in Hanoi. The project is located beside Pháp Vân - Cầu Giẽ expressway, the southern gateway of the city.