Deo Ca Group said on November 27 that advisors Bui Van Ha and Ngo Van Quy inspected the Hoang Lien road tunnel project site. The site is mobilizing 176 workers and 68 machines and equipment. On the Lai Chau side, left tunnel excavation reached 180m, right tunnel 45m, crown support 90% complete; on the Lao Cai side, the tunnel entrance has no access road and some land plots have not been handed over.

The project has total investment of 3.300 billion VND, started on December 19, 2025, length 8.8km, including main tunnel 2.63km, auxiliary tunnel 2.65km, and 11 bridges. The tunnel is designed to Japanese standards combined with Vietnamese standards, two parallel tubes 30m apart, design speed 60km/h.

According to estimates, travel time for cars will drop from 52 minutes to 11 minutes, trucks and containers from 120 minutes to 11 minutes. This is also the highest road tunnel in Vietnam, of special significance in connecting Lai Chau and Lao Cai, promoting tourism and national defense in the Northwest region.