Ministry of Construction has just reported to the Government Office on the plan to organize temporary railway operation at Phu Xuyen station, serving the work of clearing land for implementing the National Highway 1A axis project.
To ensure national railway transportation is not interrupted, Ministry of Construction proposed the Government to direct Hanoi People's Committee to accelerate the implementation of two related railway projects.
Among them, the railway renovation project Hanoi - Ho Chi Minh City section from Phu Xuyen station to Ngoc Hoi station, combined with construction of new Thuong Tin station and National Railway Transportation Operation Control Center expected completion on March 31, 2027. The railway project eastern ring road section Ngoc Hoi - Kim Son expected completion in December 2028.
Ministry of Construction also proposed Hanoi to complete the plan to upgrade existing Phu Xuyen station, invest in supporting works, ensure enough capacity and technical conditions to receive passenger transportation operations from Hanoi station and freight transportation from Giap Bat station.
The city needs to fully assess socio-economic impact, investment efficiency, and at the same time agree with Vietnam National Railway Corporation on temporary station design, train operation plan before reporting to the Government for consideration and decision.
Phu Xuyen station is located on the North-South railway line, about 35 km south of Hanoi station.
According to the plan previously proposed by Hanoi People's Committee, during the temporary operation of Phu Xuyen station, passengers will be transferred between Hanoi station and Phu Xuyen station by bus operating 24/7, all days of the week.
For goods, transfer will be carried out between Phu Xuyen station and Yen Vien station.
Hanoi People's Committee also proposed to maintain Railway Transportation Operation Control Center (OCC) at Hanoi station throughout the temporary operation period. Keeping OCC position aims to ensure train operation command is not interrupted when changing passenger pick-up, drop-off and freight transportation locations.
After the National Railway Station Complex Ngoc Hoi is completed, synchronous with urban railway items and related works, the plan to move OCC to Ngoc Hoi will continue to be studied according to planning.
In case the plan is implemented, after temporary Phu Xuyen station is completed, trial operation and meets safety and transportation capacity requirements, Ministry of Construction will inspect, organize handover of existing railway section from Phu Xuyen station to Hanoi station for Hanoi People's Committee.
The handover aims to serve the implementation of National Highway 1 expansion project combined with urban beautification and reconstruction section from Ring Road 1 to Cau Gie interchange.
National Highway 1 expansion project from Ring Road 1 to Cau Gie interchange is over 36 km long, scale of 16 lanes with total capital of nearly 162 trillion VND, expected completion in 2027. Currently the project has been implemented construction, land clearance reaches 37%.