On the afternoon of November 27, Hồ Minh Hoàng, Chairman of the Board of Directors of Deo Ca Group, led an inspection team for package XL01 of the Vinh – Thanh Thủy expressway project in Nghệ An province.
The Vinh – Thanh Thủy expressway is over 60 km long with total investment of more than 23.940 trillion VND, passing through 9 communes in Nghệ An.
Package XL01 is 6.3 km long, valued at 2.889 trillion VND, including about 4.1 km of road, Dai Huệ tunnel with two tubes each about 495 m long, and 11 bridges.
The site is deploying 15 main fronts with 131 machines and equipment and 472 workers. Completed work value reached 140 billion VND out of a total acceptance value of 2.485 trillion VND, equivalent to 5.6%. By the end of 2026, completed work is expected to reach 214 billion VND (8.6%), with acceptance and payment value expected at 170 billion VND.
At Dai Huệ tunnel, the left branch has excavated 36/495 m and the right branch 16/499 m. The project management board plans to open the east portal of the left tunnel branch on December 5, 2026 and targets full tunnel breakthrough in May 2027.
Key items including soft ground treatment, Dai Huệ bored pile construction, and tunnel excavation are meeting the required schedule.
However, in the hillside area from Km1+800 to Km2+000, residents have proposed relocation and not yet agreed to foundation excavation, disrupting work. Some locations still involve power lines and water supply pipes not yet relocated. Labor market competition makes recruitment difficult, while rebar shortage at year-end affects overtime plans.
Chairman Hồ Minh Hoàng recognized the efforts of the construction force and required the project management board to proactively coordinate with local authorities to resolve issues soon.
Upon completion, the expressway will help expand development space, strengthen regional connectivity, promote trade, tourism, logistics, attract investment, improve local and regional competitiveness, and ensure national defense and security.