General Secretary, President To Lam has inspected and checked the construction progress of projects serving the APEC 2027 High-Level Meeting in Phu Quoc. The inspection delegation included Politburo members, Secretariat members, National Assembly, Government, and local leaders.
According to the report, An Giang is implementing 21 projects serving APEC, including 11 public investment projects and 10 public-private partnership (PPP) projects, targeting completion before 30/6/2027.
Key progress figures:
| Project | Progress | Scheduled completion |
|---|---|---|
| Phu Quoc International Airport (runway No. 2) | 100% (operational) | - |
| Passenger Terminal T2 phase 1 | 84.45% | March 2027 |
| Provincial Road DT.975 (19.26 km, 10 lanes) | 65.57% | 30/5/2027 |
| LRT phase 1 (17.59 km) | 58.32% | 31/10/2027 |
| APEC Conference Center | over 79.3% | 30/6/2027 |
General Secretary praised investors and contractors for accelerating progress and ensuring quality. He emphasized the projects are modern models for the new development stage, and asked to study optimizing economic efficiency, especially non-aeronautical revenue.
He also urged An Giang province to publicly disclose the long-term Phu Quoc master plan, avoid wasteful outdated planning requiring demolition and reconstruction, and give opportunities to fast, efficient, and cost-saving contractors.