Power Transmission Company 3 (PTC3) has completed its 2026 production and business targets early under Resolution 06/NQ-HĐTV and Decision 10/QĐ-HĐTV dated January 16, 2026 of the Members' Council of Vietnam National Power Transmission Corporation (EVNNPT).

Projected full-year transmission volume reaches 9.91 billion kWh, exceeding the plan by 23.6%. As of November, the 220 kV and 500 kV transmission lines managed by PTC3 recorded no prolonged faults. Outage duration due to faults was 3.32 minutes, below the annual target of 13.12 minutes.

11-month cumulative labor productivity is estimated at 8.85 million kWh per person, exceeding the annual target by 19.1%. Electricity used for common transmission on the 220 kV and 500 kV grid is estimated at 1.88%, 0.05 percentage points below the annual target.

PTC3 completed 4,966 periodic testing items, reaching 100% of the annual plan; performed live-line cleaning at 4,858 locations while equipment remained energized.

In 2026, the company had 80 recognized initiatives and completed remote operation testing at two 500 kV substations, Vân Phong and Di Linh. At the 500 kV Di Linh substation, total substation capacity will double from 900 MVA to 1,800 MVA upon project completion.

As of November 18, investment capital executed reached 106.3% of the capital plan after review.