On the afternoon of 27/11, Chairman of the Board of Directors of Deo Ca Group Ho Minh Hoang inspected package XL01 of the Vinh – Thanh Thuy expressway project in Nghe An.

The project is over 60 km long with total investment of more than 23.940 trillion VND. Package XL01 is 6.3 km long, worth 2.889 trillion VND, including about 4.1 km of road, Dai Huệ tunnel with two tubes about 495 m each, and 11 bridges.

The construction site is deploying 15 main fronts with 131 machines and 472 workers. Completed value reached 140 billion VND out of total acceptance value of 2.485 trillion VND, equivalent to 5.6%. By end of 2026, completed value is expected to reach 214 billion VND (8.6%), with acceptance and payment expected at 170 billion VND.

At Dai Huệ tunnel, the left tube has completed 36/495 m, the right tube 16/499 m. The project management board expects to open the left tube east portal on December 5, 2026 and achieve full tunnel breakthrough in May 2027.

Main items including soft ground treatment, Dai Huệ bored cast-in-place piling, and tunnel excavation are meeting the required schedule.

Obstacles: residents in the open hill area from Km1+800 to Km2+000 have not agreed to relocation, power lines and water supply pipes have not been relocated; labor competition makes recruitment difficult; rebar shortage at year-end affects overtime plans.

After inspection, Chairman Ho Minh Hoang recognized the efforts of the construction force and required the project management board to proactively coordinate with local authorities to resolve obstacles soon, creating conditions to implement work according to plan.