Ho Chi Minh City's nearly VND 10 trillion tide control system began synchronized operation on 25 November 2026, operated by Trungnam Group from the central control center at Mương Chuối gate.

The project includes 8 large tide control gates (Bến Nghé, Tân Thuận, Cầu Kinh, Bà Bướm, Phú Xuân, Mương Chuối, Cây Khô, Phú Định) with widths from 10 to 160 meters, along with 41 small gates along about 6 km of embankment and riverside dikes. The SCADA system connects 29 monitoring stations to close gates when water rises and open them for natural drainage when the tide recedes.

When heavy rain coincides with high tide, pumping stations with total capacity of about 120 m³/s will pump water forcibly to the river, equivalent to 432,000 m³ per hour. In less than 10 minutes of continuous operation, the pumped volume can exceed 70,000 m³.

The project started in 2016, going through nearly 10 years of implementation with multiple suspensions due to site clearance and legal procedures, although actual construction volume exceeded 90%. The Government issued Resolution 40/NQ-CP (2021) and Resolution 212/NQ-CP (2025) to resolve bottlenecks and accelerate progress.

On 27–28 November 2026, 1,000 residents who registered earliest were able to visit three representative gates: Bến Nghé, Tân Thuận, and Mương Chuối.