Lang Son province is implementing the Combined Sports Complex Project with total investment of over 500 billion VND, started in August 2025 and expected to complete in 2027.

The project is built on 28.73 ha, comprising 11 construction items. Phase I focuses on building a multi-purpose arena, sports training center, athlete housing, and supporting infrastructure. The multi-purpose arena is designed with 3,000 fixed seats and 1,000 mobile seats, serving basketball, volleyball, badminton, sepak takraw, futsal, table tennis, martial arts, and gymnastics.

To date, land clearance has reached nearly 54%. 208 out of 210 affected households have been measured; compensation plans approved for 143 households with funding of more than 72 billion VND, paid to 104 households more than 41 billion VND. 135 out of 156 graves have been relocated.

Regarding construction, value of earthwork for site leveling reached about 12.5 billion VND, equivalent to over 5.5% of contract value; multi-purpose arena item reached 68% of value.

Project implementation progress is still slow. The biggest difficulty is land clearance not meeting requirements, handed-over area not contiguous.

The Provincial People's Committee requires Dong Kinh Ward People's Committee to complete compensation procedures before November 30, 2026, and at the latest by December 5, 2026 to finalize plans and land handover plans. At the same time, accelerate construction of the multi-purpose arena and sports training center to ensure construction progress and public investment capital disbursement plan for 2026.