Deputy Prime Minister and Permanent Member of the Secretariat Phạm Gia Túc concluded the meeting reviewing progress of the Long Thanh International Airport phase 1 project, assigning the Ministry of Public Security to accelerate investigation and handling of violations in project implementation, focusing on clarifying violation levels at each contract package and each construction item.

According to a report by Airports Corporation of Vietnam (ACV), the project is still facing difficulties and obstacles in acceptance and payment because some investor and contractor procedures have not been properly implemented.

Under the National Assembly-approved investment orientation, phase 1 must be completed and put into operation in 2026. The Deputy Prime Minister assigned ACV full responsibility for progress and quality of component 3 and contract packages where ACV acts as investor.

If component 3 is not completed on schedule, a report proposing schedule adjustment and special mechanisms to resolve obstacles must be sent to the Ministry of Construction before December 5.

ACV will coordinate closely with relevant agencies of the Ministry of Construction to timely implement necessary procedures to put the airport into operation and exploitation, including acceptance of completed items and works, inspection and evaluation of operating conditions, and implementation of licensing and specialized aviation approval procedures.

The Ministry of Construction is assigned to take the lead, coordinating with the Ministry of Public Security and relevant agencies to comprehensively review all necessary conditions for Long Thanh International Airport to be put into operation, ensuring absolute security and safety.

People's Committees of Ho Chi Minh City and Đồng Nai province are responsible for directing agencies to create conditions for supplying fuel, materials, and labor to prioritize contractors implementing the project upon specific proposals from ACV. The two localities also need to direct investors and contractors to soon complete connecting transport projects and fuel pipeline projects for aircraft from the source airport to the boundary of Long Thanh International Airport.

Đồng Nai province, after being authorized to approve the Long Thanh Special Economic Zone, urgently needs to develop the overall plan to deploy commercial and service zones meeting the requirements of Long Thanh International Airport operation.

Relevant ministries, sectors, and agencies will coordinate with ACV, the Ministry of Public Security, the Ministry of Construction, and Đồng Nai province to fully prepare forces, means, equipment, and necessary conditions to synchronously and effectively implement tasks related to health, tax, customs, anti-smuggling, and trade fraud prevention at the airport once the project is put into operation.

Conclusion 24 of the Politburo dated April 13, 2026 on continuing to remove difficulties and obstacles for stalled and prolonged projects approved the principle of allowing consideration, handling, and removal of difficulties and obstacles for projects simultaneously with the process of handling responsibility of organizations and individuals committing violations, ensuring no legalization of violations, no new violations arising, and having a plan to remedy damages.