Hai Phong has disbursed 36.479 billion VND in public investment capital as of November 15, ranking 3rd nationwide in terms of implementation volume. Of this, the 2026 plan capital reached 35.943 billion VND, equivalent to 93% of the Prime Minister's assigned plan and 97.3% if excluding the 5% expenditure saving item. Rollover capital disbursed was 536 billion VND, reaching 91.2% of the plan.
The Ministry of Finance evaluated Hai Phong at "Very good" level. The city sets a target to complete disbursement of capital allocated from the beginning of the year before November 30, and the additional capital will be fully disbursed in December.
Out of a total of 125 investors and localities, 78 units achieved a disbursement rate of 86% or higher. However, there are still 47 units with an implementation rate below 86%.
Regarding land clearance, as of November 15, Hai Phong has 434 projects deployed at 108 localities, with a total area needing clearance of more than 57.3 million m2, related to more than 117,700 households and 576 organizations. Localities have handed over more than 40.62 million m2, reaching 70.9% of the total area, with compensation paid of more than 25.405 trillion VND.
For 221 public investment projects under the 2026 completion plan, the land handover rate reached 80.7%. Of these, 155 projects have completed land clearance, and the remaining 66 projects are being focused on clearance.
For key traffic projects, the project serving the Lao Cai - Hanoi - Hai Phong railway line achieved a land clearance rate of 75.8%. The Hanoi - Quang Ninh high-speed railway project reached 76.3%.
To accelerate public investment capital disbursement in the coming time, Hai Phong city leaders required localities and units to act decisively, not allowing any delay in the final stage. Notably, the Department of Science and Technology was assigned to urgently upgrade the IOC system towards updating details of each project list, attaching QR codes to track progress and establishing an automatic warning mechanism for slow projects and localities.