HCMC Inspectorate issued Invitation Letter No. 2985/GM-TTTP-P7, inviting representatives of households complaining about the Contentment Plaza residential-commercial-service project (trade name Roxana Plaza, Bình Hòa ward) to attend a working session.

The working session of the inspection team under Decision No. 915/QĐ-TTCP dated October 14, 2026 of the Government Inspectorate is scheduled for 14:00 on November 30 at the HCMC Citizen Reception Office.

The Roxana Plaza project is located on National Highway 13, developed since 2017, with Tường Phong Company as the main investor. During development, Naviland Company signed 1,082 apartment sales contracts with customers, while Viethome Company participated in distribution.

Many customers were asked to re-sign contracts at 32-40 million VND/m², many times higher than the initial purchase price of about 20-21 million VND/m².

Previously, Inspection Conclusion No. 308/KL-UBND dated August 22, 2023 of Bình Dương Province People's Committee required Tường Phong Company to continue implementing apartment sales contracts signed by Naviland with customers, and to complete the project according to the approved schedule.

On October 9, 2026, HCMC People's Committee issued Notice No. 590/TB-UBND on terminating the review, handling, and resolution of petitions and feedback related to the Roxana Plaza project at administrative agencies, as contract disputes are under the jurisdiction of the courts.

At the HCMC Council session on October 30, deputy Trần Thành Trọng continued to urge relevant agencies to definitively resolve the Roxana Plaza issues and protect homebuyers' rights.

Responding to the deputy, HCMC Department of Finance leadership stated the investor must implement the inspection conclusion contents. The proposal to adjust investment orientation and extend the investor's schedule up to that time has not yet been approved.