The new Mai Lĩnh Bridge is about 1.03 km long, with 10 piers, designed for 4 motor vehicle lanes, double the number of lanes of the existing bridge. The bridge connects Chương Mỹ and Yên Nghĩa wards, crossing the Đáy River, and is scheduled to open partially in early December 2026.

The bridge belongs to the National Route 6 expansion project from Ba La to Xuân Mai, with a total length of about 21.7 km, cross-section width of 50-60 m, and total land clearance area of 105.872 hectares. The project started construction in June 2025.

However, the project is still classified as slow progress, with construction completed at only 22.9% of the plan. Contractors are concentrating labor and machinery to complete the right side of the bridge. The pier system on both banks has basically been concreted, many positions have installed beam slabs and moved on to bridge deck construction.

Since National Route 6 must maintain traffic during construction, the new Mai Lĩnh Bridge is built in stages. After the right side is completed and put into operation, the old bridge will be demolished to deploy construction of the left side.

When fully completed and put into operation, the project is expected to increase traffic capacity at Hanoi's southwestern gateway, help reduce prolonged congestion, expand urban space, and strengthen transport connectivity between Hanoi and neighboring localities.