On November 27, Vice Chairwoman of Dong Nai People's Committee Nguyen Thi Cat Tien chaired a meeting to review land clearance progress for the Dau Giay - Tan Phu expressway project.

According to the Dong Nai Land Development Fund Center, the project needs to acquire over 390 hectares of land. To date, localities have handed over nearly 373 hectares to investors, reaching over 95% of the total area. The remaining area is mainly in sections passing through Phu Hoa and Phu Lam communes.

For the unhanded area, localities have approved compensation and support plans. However, due to insufficient additional budget for land clearance, there is no funding to pay households. The Land Development Fund Center proposed the investor consortium and the Northern Highway Project Management Unit to promptly allocate sufficient funds for compensation and support, ensuring land handover progress.

Representatives of wards and communes along the expressway proposed planning and investment in feeder roads and drainage systems to ensure travel, living, and production for residents while minimizing impact on residential areas. The investor consortium requested the city to direct agencies to resolve difficulties in permitting material quarries and arranging waste disposal sites.

Vice Chairwoman Nguyen Thi Cat Tien urged the consortium and project management unit to urgently allocate full funds, transfer budgets to localities for compensation payments, and complete land clearance along the entire route. Localities must urgently review all investment needs for feeder roads, drainage, and related infrastructure, then submit reports to the Department of Construction for city review and additional investment where truly necessary.