The Vành đai 3,5 - Thăng Long Avenue interchange in An Khánh, Hanoi, has been under construction for over a year since April 2025. Total investment over 2,300 billion VND (about 2,384 billion VND), investor is Hanoi Civil Construction Project Management Board.
The project uses cloverleaf model combining flyovers and underpasses. 4 flyover branches over 2.3 km long, each 8.8 m wide, two lanes. Underpass about 150 m long serves direction from Hoàng Tùng Street to National Road 32.
Construction volume about 38% complete. 1,000 mm bored piles finished 293/310 (about 95%); all 28/28 1,500 mm piles completed. Pile caps finished 68/80, column shafts 67/80. Progress of 4 flyover branches: 39%, 35%, 44%, and 40%. Enclosed tunnel HK4A 11%, open tunnel sections 9/15 (56%).
Issues: land handed over 195,673.6 m² of total 196,016.5 m² (99.8%), remaining 342.9 m² of 3 households in Tây Mỗ ward not handed over, affecting pile 4P5 of branch 4 and 120 m road section. Underground 110kV and 220kV power cables crossing construction site also cause difficulties.
Construction contract deadline July 2027, project expected completion in 2027.