The Government Office has just issued Notification No. 591/TB-VPCP dated 26/11/2026 on the conclusion of Deputy Prime Minister Phạm Gia Túc at the meeting related to the proposal to implement the Hanoi railway industrial park investment project.

According to Hanoi's opinion, based on the Capital Law, the city has the authority to hand over the railway industrial park project to investors to meet the urgent schedule for assembling vehicles serving five urban railway projects under implementation.

If the city decides to invest in the project, it is proposed to coordinate with the Ministry of Construction to unify the investment plan, scope, scale, functions, and tasks to meet common needs for all types of railways and take responsibility for efficiency and feasibility. At the same time, coordinate with relevant ministries and agencies to consider, within their authority, the investor's proposals according to legal regulations.

Notably, Vingroup Group (HoSE: VIC) is the project investor for the railway industrial park in Phú Xuyên commune, with total capital of about 29.637 billion VND, excluding estimated site clearance costs of about 4.000 billion VND.

The project has a land use scale of about 280 hectares, estimated construction density of 50%, aiming to form a factory complex producing equipment, components, and parts for the railway industry, combined with research, technology transfer, training, and quality testing.

In particular, the project is implemented to serve five railway lines 1, 2, 8, 10, and 14, with an estimated total length of about 253.5 km, total investment of over 1 quadrillion VND (nearly 39 billion USD).

The consortium of Vinhomes JSC (HoSE: VHM) and SGC Investment and Construction JSC has been assigned the turnkey package worth 873.224 billion VND (about 33.8 billion USD). The contract execution period is 51 months on a turnkey basis, expected to complete before 31/12/2030.

To prepare for project implementation, the Vinhomes-SGC consortium has ordered a large-scale system of specialized construction machinery and equipment, including more than 100 TBM tunnel boring equipment lines and more than 50 diaphragm wall equipment lines.

The consortium also plans to mobilize thousands of excavated soil and slurry transport vehicles to meet the requirements of simultaneous construction at many sites.

In addition, the consortium is cooperating with consulting units from Europe, Japan, South Korea, and China to develop detailed designs for these projects.